Reasonableness of a condition requiring development contributions

The option of testing the reasonableness of a section 7.11 contributions condition in the Land and Environment Court is now more attractive for development of $10 million or more because the payment of any monetary contribution is deferred until prior to the issue of an occupation certificate, rather than a construction certificate.

The reform of development contributions in New South Wales has been in the spotlight since the New South Wales Productivity Commission published its Final Report on its Review of Infrastructure Contributions in New South Wales in late 20201, the release of the New South Wales Government‘s response to that report in March 20212, and the introduction into the New South Wales Parliament in late June 2021 of the Environmental Planning and Assessment Amendment (Infrastructure Contributions) Bill 20213 which is now subject to a parliamentary committee review.

In the meantime, developers should keep in mind that there is available to them the ability to test in the Land and Environment Court the reasonableness of a section 7.11 contributions condition (but not a section 7.12 contributions condition4).

This option has not always been attractive because of the consequential delay it causes in the issue of a construction certificate. 5However, that timing disincentive does not currently apply to development with an estimated cost of $10 million or more. 6This is because the payment of any monetary contribution required by a section 7.11 condition for certain development7 is deferred until prior to the issue of an occupation certificate, rather than a construction certificate.8

Any section 7.11 condition could be appealed to the Court:

  • Against the development consent (but this is often not the preferable option9); or
  • Against the deemed or actual refusal of any section 4.55 application seeking amendment of the section 7.11 condition.10

The Court has a broad discretion and can disallow or amend the condition because it is unreasonable in the particular circumstances of the case . Provided cogent evidence is presented, the Court can amend or impose a section 7.11 condition that is not determined in accordance with the relevant contributions plan.

Unreasonableness of any section 7.11 condition

Reasonableness is to be tested according to its ordinary meaning.12 As the law currently stands, the unreasonableness must arise by the application of the contributions plan and not due to other circumstances.13 Below are some Court examples.

Examples where the Court has found the contribution condition is unreasonable

  • Nexus: The proposed subdivision did not generate the need for the conservation corridor the subject of the contributions plan.14
  • Double dipping: A Commissioner held that the contribution conditions imposed on five development consents for the subdivision of land in a release area were unreasonable. Approximately 50% of the release area had already been developed and contributions paid in accordance with the former contributions plan. The new, relevant contributions plan sought substantially higher contributions for the same facilities the subject of the earlier plan.15
  • Disconnect between amount and scope of works sought by the Council and the contributions plan: The Court held that the condition was not reasonable because the amount in the conditions was calculated based on a cost estimate and works not referenced by the Council’s adopted and published contributions plan.16
  • Miscalculation: Where the contribution is determined by the number of road trips, applicants have been able to successfully prove to the Court that the number of road trips applied by the relevant council in calculating the contribution is excessive.17
  • Amended development: The Court reduced the contribution towards the payment of car parking because a modification of the development consent removed the residential component of the approved development.18

Examples where the Court has found the contribution condition is not unreasonable

  • No double dipping: The Court rejected an offset of the cost of providing a public car park in the development against the contribution sought to be imposed by the council pursuant to a contributions plan for local roads, public transport facilities, open space and recreation community facilities. The Court was not satisfied that the car park was an in-kind contribution contemplated by the contributions plan. Also, in this case the developer received the benefit of an additional two storeys by constructing the car park.19
  • Material public benefit not considered: A consent condition required the applicant to carry out the construction of a roundabout that would not only benefit the proposed subdivision but would provide a public benefit. The value of the roundabout works exceeded the contribution required to be paid.. The applicant was unsuccessful in seeking to reduce the amount of contributions payable to take into account the value of the material public benefit works required by the consent.20
  • Delay in determination of the development application: The applicant argued unsuccessfully that the contribution condition was unreasonable because the Council delayed in assessing and determining the development application. Had the application been determined before the lifting of the $45,000 cap per lot, the contribution required by the contributions plan would have been approximately $900,000 less. The Court held that any “unreasonableness” in the actions of the Council is not within the meaning of “unreasonable” in section 7.13(3).21
  • Insufficient evidence: The Court rejected the applicant’s submission that a monetary contribution for roadworks for an additional dwelling was unreasonable because no evidence was provided to the Court as to what the trip generation of the approved development would be or why a future occupant would not utilise the road network.22

1 Policy and Guidelines Paper TPP (nsw.gov.au)
2 NSW Government Response to NSW Productivity Commission’s Review of Infrastructure Contributions in NSW – March 2021
3 Environmental Planning and Assessment Amendment (Infrastructure Contributions) Bill 2021 (nsw.gov.au)
4 Section 7.13(4), Environmental Planning and Assessment Act 1979 (EP&A Act).
5 Section 7.11 conditions ordinarily require that any monetary contribution must be paid before the issue of any construction certificate.
6 The estimated cost is for the purposes of calculating the DA fee in accordance with the Environmental Planning and Assessment Regulation 2000 .
7 Clause 4(2), Environmental Planning and Assessment (Local Infrastructure Contributions – Timing of Payments) Direction 2020 dated 25 June 2020. The Direction expires on 31 March 2022: section 10.17(7), EP&A Act.
8 Due to the COVID-19 pandemic. However, the deferral is likely to be made permanent following the NSW Government’s acceptance of the Productivity Commission’s recommendation 4.10.
9 Because you cannot act on the consent pending the appeal, as the consent ceases to have effect (section 8.13(1)) you lose the time advantage and you potentially risk the whole consent.
10 Rose Consulting Group Pty Ltd v Baulkham Hills Shire Council (2003) 58 NSWLR 159 per Santow JA at [34]- [35] (with whom Meagher JA and Young CJ in Eq agreed).
11 Section 7.13(3).
12 Rose Consulting v Baulkham Hills Shire Council (2003) 58 NSWLR 159 at [49].
13 Colonial Credits Pty Ltd v Pittwater Council [2015] NSWLEC 188 per Moore AJ (as his Honour then was) at [48]; Intrapak Skennars Head Pty Ltd be Ballina Shire Council [2021] NSWLEC 1006 and TC (Tallwoods) Pty Limited v Camden Council [2021] NSWLEC 1212.
14 Lake Macquarie City Council v Hammersmith Management Pty Ltd [2003] 132 LGERA 225
15 The Commisisoner also held that the facilities provided for an unreasonably high standard of provision. A judge of the Court overturned the Commissioner’s decision, and the Court of Appeal overturned that judge’s decision: Rose Consulting v Baulkham Hills Shire Council [2003] 58 NSWLR 159.
16 Vortex Property Group (NSW) Pty Ltd v Georges River Council [2019] NSWLEC 1153 at [119]
17 The Lawson Clinic Ltd v Ku-ring-gai Council (No 2) [2016] NSWLEC 65; Wilson v Mid Coast Council [2018] NSWLEC 2018.
18 Onodi v Canada Bay Council [2005] NSWLEC 524.
19 Olsson v Ashfield Municipal Council [2012] NSWLEC 1073.
20 Intrapak Skennars Head Pty Ltd be Ballina Shire Council [2021] NSWLEC 1006.This decision is subject to appeal.
21 TC (Tallwoods) Pty Ltd v Camden Council [2021] NSWLEC 1212 per Clay AC at [105].
22 Young v Ballina Shire Council [2019] NSWLEC 1131.7

Liability limited by a scheme approved under Professional Standards Legislation.
© ADDISONS. No part of this document may in any form or by any means be reproduced, stored in a retrieval system or transmitted without prior written consent. This document is for general information only and cannot be relied upon as legal advice.